Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

What did the constitution of the clergy do?
The perimeter of a rectangle is 78cm. Its longest side has a length of 22cm. State the length of the shortest side
hi how are you doing today?
Need help with this answer
Having two, or even three, people explain the material to you a will help you understand it c. will just confuse you. Its better to only ask one person to help
Match the numbers to their equivalent alternate form. 1. 1/1000 0.1% 2. 110% 125% 3. 5 4. 0.5 2/3 4/25 7 5. 20 6. 1.1 0.08 7. 16% 1/80 8.1.25% 0.35 9. 60% 10. 2
if the area of a circle measures 25 TT cm2 what is the circumference of the circle in terms of TT A) 5 TT cm B) 10 TT cm C) 50 TT cm D) 100 TT cm
what is mitosis and meiosis​
I got one but someone plz help me with the rest I will give brainly to the first person to answer right. Classify each polygon by its number of sides. Drag the
How can a wave carry information? A. The transmitter changes the form of the wave. The receiver then decodes the changes that have been made to the wave. B. Th