5. If 15 men can finish a work in 16 days in how many days will 8 men can finish the same work? a. 15 b. 20 c. 30 d. 42​

Respuesta :

davism19 davism19
  • 02-08-2022

Answer:

C. 30

Step-by-step explanation:

15 men do work in 16 days

This means that 7.5 men (15/2) would do that same work in 32 days (16x2).

If the number of men increase, the amount of days decrease.

8 men would do that work in 30 days

8 men > 7.5 men

30 days < 32 days

Answer Link
profereyes12122
profereyes12122 profereyes12122
  • 05-08-2022

Answer:

Option c.

Step-by-step explanation:

It is an inverse proportion, fewer workers more days to finish the job.

15 -----16

8 ----- x

x = (16)(15)/8 = 240/8 = 30 days

Hope this helps

Answer Link

Otras preguntas

PLEASE HELP QUICK!!!!! WILL GIVE BRAINIEST!!!!!
Please select the word from the list that best fits the definition Worker who was tied to the land Next Submit Save and Exit Mark this and return
What is the Active Voice of : How was the heavy table pushed away by you?
Which statement best completes the diagram?
Rewrite the following sentences logically, adding an appropriate adjective from the list below. Be sure to make the adjective agree with the noun it describes a
Please help me with this problem. will give branlist.​
In the diagrams, the pre-image is shown with a dested tree and the image is shown with a solid line which transformation represents a dilation? .​
¿Cuál es la corriente más grande que puedes crear?
HELP ILL GIVE BRAINLIEST PLZ HELP
43) A truck goes from 0-55 mph in 3.2 seconds. A change in velocity over time is... a)speed c)friction b) inertia d)acceleration