thirty-six men can paint a shopping mall in 25 days. How many days will it take 15 men to paint the mall, if they work at a same rate?​

Respuesta :

ksperu ksperu
  • 04-05-2021

Answer:

12.5 days

Step-by-step explanation:

Given

No of workers= 30

Time taken to paint shopping mall= 25 days

Assume time taken for 15 men =X

Time taken for 15men to paint X= (15*25)/30

=12.5 days

Answer Link

Otras preguntas

a long distance telephone company charges a rate of 8 cents per minute or 90 cent mininum charge per call, whichever is greater. Find the cost in cents per minu
If A+B=76  and A -B=38 whats A divided by B
what were the four main causes of the Cold War
What is NAFTA? What countries are involved?
Why can't we change the subscripts in balancing chemical equations?
In scienceclass the teacher measured 800 milligramns of an chemical.How manyn grams is it.
How did the Romans rule differently from the Etruscans?
Which text exemplifies the anti-Victorianism prevalent in the early twentieth century? a) Eminent Victorians b) Jungle Books c) Philistine Victorians d) The
What is the volume of a rectangular box that has base area of 75 square inches and a height of 20 inches
How do you think the people conquered by the Romans felt about their new rulers