a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

Element A has 15 protons. Determine the number of neutrons in its isotope with mass number 33
How is the principle of states' rights reflected in the Declaration of Independence or the Articles of Confederation? give an example from either the Declaratio
Antointette puts the letters of her name inside a bag and picks one letter at random what is the probability that Antoinette picks a vowel​
(x+9)(x+2)=4(x+9) what is the value ofx​
where did natchez live in Mississippi ​
The United States has a type of government known as a democratic republic. This is different from a direct democracy in that
How are the italicized words in this sentence related? On Sunday, Marcus ate dinner at eight with his friends from down the street. They are idioms. They are an
The Bill of Rights is primarily concerned with which principal of the constitution *
Why did the Europeans settled in the America’s?
Need help as soon as possible